 Project Name
Priority
Estimated Completion
 Current Progress
 Notes
Wireless Phones
N/A No Date set
Testing new phone model
 
Printers - Job Hold
N/A
October 25
Complete
 
Phone System
1 August 12, 2011
Complete
 
Wireless - Captive Portal
 N/A Dec 15,2011
Complete
New Landing Page
3 November 18, 2011
Complete
 Tied to project below
Move ARGS.US website to cloud
N/A
No date set
Evaluation
 
Evaluate Terminal Services
N/A
Will not work at ARGS
Complete
 Tied to project below
Creative Suite
2 April 18, 2012
Testing  
E-Rate Filing
1
ASAP
Trial Year - late filling  
Chromebooks 3 School Year 2012-13
Complete
 
Replace Proxy Server 3 No date set    
Guest Wireless Access 3 Jan 15, 2012 Complete Alumni/Non-ARGS Access
Google Cloud Print 3 Jan 15, 2012 Beta to Staff Printing from Google Chrome
Priority 1-5: 1 being the highest

Notes/Log:
Oct 20, 2011: Printers - Job hold - New completion date - October 25 from December 1, 2011
Oct 20, 2011: Wireless Phones - New Completion date - December 15, 2011 from December 1, 2011
Nov 1, 2011: Creative Suite now pricing/clp
Nov 4, 2011: Printers - Job - changed from Deployment to Complete
Nov 4, 2011: Changed Landing Page to priority 3 from N/A
Nov 4, 2011: Changed Wireless - Capitve Portal from Evaluation to Infrastructure Upgrades, completion date to Jan 15, 2012
Nov 8, 2011: Added E-Rate Filing
Nov 10, 2011: Deployed New Landing Page
Nov 16, 2011: Captive Portal changed current progress from Infrastructure upgrades to Researching login system. Completion date changed from Jan 15, 2012 to Dec 15, 2011
Nov 16, 2011: Chromebook project added
Nov 18, 2011: Wireless Phone project progress changed to Switching phone models from Testing
Nov 30, 2011: Changed Captive Portal to security testing.
Dec 9, 2011: Changed Wireless phone from Dec 15, 2011 to no date set
Dec 13, 2011: Added Replace Proxy Server, no date set
Dec 14, 2011: Added Guest Wireless Access, Changed Captive Portal to Complete, changed Landing page to complete
Dec 14, 2011: Changed Guest Wireless Access to complete
Dec 14, 2011: Added Google Cloud Print with No date set, security testing
Jan, 10, 2012: Creative Suite changed to P.O./Quotes from CLP/Pricing
Jan 10, 2012: Changed Evaluate Terminal Services to Testing from Ordering
Jan 12, 2012: Changed Google Cloud Print to "Beta to staff" this is complete but with some testing at a larger level
Feb 14, 2012: Changed P.O./Quotes for Creative Suite to Ordered
Feb 22, 2012: Change Terminal Services to complete.
Feb 22, 2012: Changed Chromebooks from Testing to Complete. Will not be able to purchase until 2012-13 SY
April 4, 2012: Changed Wireless phones to testing new model
April 4: 2012: Changed E-Rate from File 470 to Trial Year - Late filling
April 4: 2012: Changed Creative Suite from Ordered to Testing, completion date from April 15 to April 18