This page lists all the projects currently on-going with ARGS I.T. and their estimated completion time/date.
Notes/Log: Oct 20, 2011: Printers - Job hold - New completion date - October 25 from December 1, 2011 Oct 20, 2011: Wireless Phones - New Completion date - December 15, 2011 from December 1, 2011 Nov 1, 2011: Creative Suite now pricing/clp Nov 4, 2011: Printers - Job - changed from Deployment to Complete Nov 4, 2011: Changed Landing Page to priority 3 from N/A Nov 4, 2011: Changed Wireless - Capitve Portal from Evaluation to Infrastructure Upgrades, completion date to Jan 15, 2012 Nov 8, 2011: Added E-Rate Filing Nov 10, 2011: Deployed New Landing Page Nov 16, 2011: Captive Portal changed current progress from Infrastructure upgrades to Researching login system. Completion date changed from Jan 15, 2012 to Dec 15, 2011
Nov 16, 2011: Chromebook project added
Nov 18, 2011: Wireless Phone project progress changed to Switching phone models from Testing
Nov 30, 2011: Changed Captive Portal to security testing.
Dec 9, 2011: Changed Wireless phone from Dec 15, 2011 to no date set
Dec 13, 2011: Added Replace Proxy Server, no date set
Dec 14, 2011: Added Guest Wireless Access, Changed Captive Portal to Complete, changed Landing page to complete Dec 14, 2011: Changed Guest Wireless Access to complete
Dec 14, 2011: Added Google Cloud Print with No date set, security testing
Jan, 10, 2012: Creative Suite changed to P.O./Quotes from CLP/Pricing Jan 10, 2012: Changed Evaluate Terminal Services to Testing from Ordering Jan 12, 2012: Changed Google Cloud Print to "Beta to staff" this is complete but with some testing at a larger level Feb 14, 2012: Changed P.O./Quotes for Creative Suite to Ordered Feb 22, 2012: Change Terminal Services to complete. Feb 22, 2012: Changed Chromebooks from Testing to Complete. Will not be able to purchase until 2012-13 SY April 4, 2012: Changed Wireless phones to testing new model April 4: 2012: Changed E-Rate from File 470 to Trial Year - Late filling April 4: 2012: Changed Creative Suite from Ordered to Testing, completion date from April 15 to April 18 |